Scrap Tire Derived Fuel/Substitute Fuel
A Tire Derived Fuel or Substitute Fuel Facility Approval is for permission to utilize scrap tires (whole or chipped) as a fuel or supplemental fuel.
- Expected Fee
- $0
- Duration
- 9 Months
Obtaining the permit
- Step 1:
- Submit a complete application form
- Step 2:
- Proof of Workers’ Compensation
- Step 3:
- Economic Demonstration
- Step 4:
- Description of facility opearations
- Step 5:
- Facility topographic information and conceptual design
- Step 6:
- Scrap tire storage
- Step 7:
- Closure plan
Want to apply for the permit?.
Apply NowWant to learn more about the permit?
Contact Details
Scrap Tire Derived Fuel/Substitute Fuel
A Tire Derived Fuel or Substitute Fuel Facility Approval is for permission to utilize scrap tires (whole or chipped) as a fuel or supplemental fuel.
- Expected Fee
- $0
- Duration
- 9 months
Obtaining the permit
- Step 1:
- Submit a complete application form
- Step 2:
- Proof of Worker's Compensation
- Step 3:
- Economic Demonstration
- Step 4:
- Description of facility operations
- Step 5:
- Facility topographic information and conceptual design
- Step 6:
- Scrap tire storage
- Step 7:
- Closure Plan
Want to apply for the permit?.
Apply NowWant to learn more about the permit?
Contact Details
Scrap Tire Derived Fuel/Substitute Fuel
A Tire Derived Fuel or Substitute Fuel Facility Approval is for permission to utilize scrap tires (whole or chipped) as a fuel or supplemental fuel.
- Expected Fee
- $0
- Duration
- 9 Months
Obtaining the permit
- Step 1:
- Submit a complete application
- Step 2:
- Proof of Worker's Compensation
- Step 3:
- Economic Demonstration
- Step 4:
- Description of facility operations
- Step 5:
- Facility topographic information and conceptual design
- Step 6:
- Scrap tire storage
- Step 7:
- Closure Plan
Want to apply for the permit?.
Apply NowWant to learn more about the permit?
Contact Details
Scrap Tire Derived Fuel/Substitute Fuel
A Tire Derived Fuel or Substitute Fuel Facility Approval is for permission to utilize scrap tires (whole or chipped) as a fuel or supplemental fuel.
- Expected Fee
- $0
- Duration
- 9 Months
Obtaining the permit
- Step 1:
- Submit a complete application form
- Step 2:
- Proof of Worker's Compensation
- Step 3:
- Economic Demonstration
- Step 4:
- Description of facility operations
- Step 5:
- Facility topographic information and conceptual design
- Step 6:
- Scrap tire storage
- Step 7:
- Closure Plan